We have a Unity API written for OnBase v12.
We will be upgrading to v13 soon.
App Enabler and Unity will upgraded to v13...our client upgrade will be incremental..so not all client will be on v13 day one after upgrade.
Will v12 clients still be able to access the API funcionality pointed to the v13 database?
Thanks
04-08-2014 05:15 AM
Hi Greg,
That is true. The Application server is backwards compatible with v12. Clients using the v12 Hyland.Types.dll and Hyland.Unity.dll in an application should not experience any interruption when connecting to the new application server.