Is possible to deploy a new process, and don't create a new version, specifically for this deploy?
Or, in this case, is better to control it manually, removing all process definitions (and their process instances) of a process key before deploy the new one?

My intention is deploy a process many times during its construction, to do tests, and I don't need to create many different versions in this case.
Any other suggestion of a betther approach is welcome.

Thanks.
1 REPLY 1

trademak
Star Contributor
Star Contributor
No, Activiti always creates a new version when you deploy a process definition. From what you are describing it sounds like you need a specific test environment, and then deploy it to a production environment when everything is tested and you don't need to deploy a new version that often.

Best regards,