Hi, I have designed a process and now would like to add parts of it into a subprocess so that I can attach a error boundary event on it (I hope this is the
way how it is meant to be done).
How can I do this in the designer without having to recreate all models within the sub process? I would prefer to select the elements I want to have in the sub process
and then say something like right-click "create sub process around selected elements". Is this possible?
The reason for this is that I have many user tasks where I want to allow the user to end the process and I don't want to model a sequence flow for each of this
because it messes up the process design.
many thanks in advance,
Chris
way how it is meant to be done).
How can I do this in the designer without having to recreate all models within the sub process? I would prefer to select the elements I want to have in the sub process
and then say something like right-click "create sub process around selected elements". Is this possible?
The reason for this is that I have many user tasks where I want to allow the user to end the process and I don't want to model a sequence flow for each of this
because it messes up the process design.
many thanks in advance,
Chris
Labels:
- Labels:
-
Archive
2 REPLIES 2

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-12-2011 01:44 PM
Right, this is no supported functionality in the Activiti Designer. It may be a good idea to create a JIRA for it.
Best regards,
Best regards,
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-26-2011 10:05 AM
Hi, I create a Jira improvment ticket for this: