Does Activity support queues and time spent on each task.

padmahas
Champ in-the-making
Champ in-the-making

I need couple of clarifications.

  1. Does Activiti supports queuing a task and/or reassigning a task to others?
  2. Does Activiti logs time spent, on each process steps and provides "cycle time"?
1 ACCEPTED ANSWER

ycoulon
Employee
Employee

Hi,

Yes it's possible to reassign a task.

About time spent in task, there is an history feature in activiti that would answer your question.

To get more informations about that check the activiti documentation Activiti User Guide section 11 and 15.8.

Regards

View answer in original post

2 REPLIES 2

ycoulon
Employee
Employee

Hi,

Yes it's possible to reassign a task.

About time spent in task, there is an history feature in activiti that would answer your question.

To get more informations about that check the activiti documentation Activiti User Guide section 11 and 15.8.

Regards

padmahas
Champ in-the-making
Champ in-the-making

Thank you for correct answer and thank you for the reference Yann.