Hi,

The inclusiveGateway does not work correctly with two subprocesses.

Below is my process design.[attachment=2]InclusiveGateway.png[/attachment]

With this diagram, if I complete Task1, then only Task2 should be in waiting task,

but the result is that Task3 and Task2 is waiting().

It seems that the inclusiveGateway does not join correctly with 2 subprocesses.

I attached the design file and test code.

Best regards.
5 REPLIES 5

steve1
Champ on-the-rise
Champ on-the-rise
I think this may be a bug.

Should I file a jira issue?

trademak
Star Contributor
Star Contributor
Hi Steve,

Yes this definitely looks like a bug. Please create a JIRA.
Thanks for the test and the process example, that's very helpful.

Best regards,

steve1
Champ on-the-rise
Champ on-the-rise
Filed a jira: http://jira.codehaus.org/browse/ACT-1204

Best regards,

patg
Champ in-the-making
Champ in-the-making
Hi,
I have the same issue if instead of 2 subprocesses I have 2 call activities. (using Activiti 5.10)

smirzai
Champ on-the-rise
Champ on-the-rise
Fixed. See related Jira issue