Is it possible to complete a task and then say which transition the engine should use, like in jbpm 3?

getJbpmTaskInstance().end(transitionName);

Greets cookie-exploit
2 REPLIES 2

ronald_van_kuij
Champ on-the-rise
Champ on-the-rise
O, since that is not 'bpmn' compliant. Search the forum for comparable questions and answers (set a process variable anduse a gateway behind the usertask)

cookie-exploit
Champ in-the-making
Champ in-the-making
Thanks for reply, thats the same I thought about.

I intend to use  variable with the name of the transition and gave it true as value. But it could have been, that Activiti offers another possibility to do this.