Hi,

In 2011, it was not possible to do embedded subprocess. (http://forums.activiti.org/content/embedded-sub-processes)

Now Is it possible to design subprocess in two different diagrams ?

I have tried the container "callActivity" but when I click on the button in order to choose one of all found process, the open dialog is empty.

Thank you for your helps.

Alex
7 REPLIES 7

ascott42
Champ in-the-making
Champ in-the-making
I Have also note in the book Activiti in action, that it is possible to run two versions of a process into BPM engine. But when I create a new process diagram with the plugin, there is no information concerning the version ?

Thnaks.

ascott42
Champ in-the-making
Champ in-the-making
The dialog box was empty because it was not an activiti project.

But with a new project, when I save the diagram, the field "Called Element" become blanck again.

Is it a bug ?

Thanks for your helps.

trademak
Star Contributor
Star Contributor
It works okay on the trunk version of the Designer. Which version are you using?

Best regards,

ascott42
Champ in-the-making
Champ in-the-making
V 5.12.0

matpil
Champ in-the-making
Champ in-the-making
Hi,
seems that I've the same problem…
I try to replicate what done in this post (http://bpmn20inaction.blogspot.it/2013/03/activiti-designer-5120.html) but the list of call element is empty (I've other 4 bpmn files in the same folder!)

I use eclipse kepler 4.3, eclipse activiti plugin 5.12 and activiti 5.11

Any suggestion?

Regards


matpil

trademak
Star Contributor
Star Contributor
Kepler is not supported. Right now Indigo and Juno are supported.

Best regards,

matpil
Champ in-the-making
Champ in-the-making
ok, thanks for reply